Foundation Park North welcomes Avera Health and Owens & Minor, infrastructure development underway

  • October 2, 2023

We’re closing out the 3rd quarter on a high note with the announcement of Avera Health and Owens & Minor as the newest tenants in Foundation Park!

The 23-acre site will be home to a shared facility for the two healthcare organizations. It will allow for greater efficiencies for Avera and closer service for other regional health care clients of Owens & Minor.

The Foundation’s long-term vision, strategy, and planning for infrastructure and improvements in Foundation Park has proved successful as this is the first tenant north of the rail line.

According to Joe McSweeney, a partner in the project’s developer, Brookwood Capital, the land is “really served with utilities, and it’s ready to go, and I would credit the Foundation with that because they anticipated the demand and had the vision to design roads and start roads and bring utilities, so when a tenant comes along, they’re ready to close on the land and have everything you need there.”

Hear more from the project’s partners here.

Below are more updates on Foundation Park’s infrastructure.

Foundation Park North – Street Construction

All the sanitary sewer, water main, storm sewer and drop inlets are installed along Sechser Avenue and Memory Lane. Soukup Construction has also begun placing cement stabilization along Sechser Avenue and Memory Lane.

Next, Soukup Construction will finish placing cement stabilization west on Memory Lane towards Marion Road. When the cement treatment is finished, they will begin placing the aggregate base course.

Foundation Park North – Trunk Sanitary Sewer

Lidel Construction has placed all trunk sanitary sewer along the railroad alignment to 259th Street. Now, they are installing 15” trunk sanitary sewer north along the Interstate alignment. Currently, Lidel Construction is about 1,500’ south of 259th Street.

Xcel Power Pole Relocation

Xcel Energy has relocated all power poles along 259th Street except for the far east pole. In addition, all but three (3) of the existing power poles have been removed. Xcel plans to wrap up their work by the end of September. John Riley Construction plans to finish the remaining grading work along 259th Street by late September or early October.

Upsize Existing Trunk Sewer (south of the RR)

The design is in progress and will be completed by the end of September for submittal to the City for review/approval.